A buyer may think a RERA penalty means their money will automatically come back. A 17 November 2026 Telangana RERA order involving Sanali The Edge, at Manchirevula near Hyderabad, shows why that assumption can be costly.
Quick answer: Telangana RERA found that Sanali IT Parks and its managing partner marketed apartments before the project was registered. It imposed a ₹25 lakh penalty and directed the respondents to stop marketing or selling units until registration. The authority did not grant the complainants’ requested refunds in these proceedings, because their payments had been used to buy land registered in their names. Resolving those land rights would require a different legal forum. This is a finding about these transactions, not a rule that buyers in every unregistered project cannot obtain refunds. Read the official order.