A construction photograph can look reassuring without telling you when it was taken or which tower it shows. For a Mumbai flat under construction, the date and scope of the MahaRERA update are as important as the headline progress figure.

Quick Answer

Find the registered project on MahaRERA and identify the building or wing containing your proposed flat. Read the latest available update date, task or activity progress, uploaded documents and building-wise completion date. Then compare those disclosures with a current authorised site visit and the promoter’s written explanation of remaining work. A percentage alone is not a completion certificate or a guaranteed possession date.

Updated: 27 October 2026.

What You Will Learn

• Which fields in a project update deserve attention.

• Why the exact building and reporting date matter.

• How to ask useful follow-up questions after a site visit.

First Match the Project Identity

Large developments can have several phases, towers and registration numbers. Obtain the RERA number from the promoter’s current project material and search it on MahaRERA. Confirm the promoter, location and building or wing before reading progress data. A completed tower elsewhere in the development cannot establish the status of your proposed flat.

Read the Update as a Dated Record

MahaRERA’s project-update guidance lists areas such as project cost, document uploads, building details, task or activity work percentage, common areas and facilities, and building-wise completion dates. Note the reporting period and the date on which the information was last made available.

A quarterly update is a snapshot. Work can change after it. If the visible record is old, request a newer written status and ask why the portal has not yet reflected it. Do not infer from age alone that construction has stopped.

Separate Structure, Services and Possession

An exterior that looks almost finished may still need internal work, lifts, utilities, common areas, testing or applicable approvals. Ask what remains for your particular building and for the services promised in your agreement.

For each item, ask for a measurable answer. “Finishing work” is vague; “lift testing pending in Tower B” identifies a task you can follow up. Keep the proposed completion date separate from any sales conversation about expected key handover.

Compare Record and Reality

During an authorised visit, observe the building containing your unit, access areas and visible common facilities. Photograph only where permitted. Record the date and ask the promoter to reconcile material differences between the site and the official update.

Also inspect uploaded documents and disclosed encumbrances where relevant. A progress percentage does not replace document review, technical inspection or your contract.

Make a Decision With a Short Evidence File

Keep the project registration details, a dated copy of the relevant MahaRERA update, the promoter’s current written status and your site-visit notes. If dates or building descriptions conflict, resolve them before treating a handover estimate as settled.

Frequently Asked Questions

Q: Does “80% complete” mean possession is near?

A: Not by itself. Ask which tasks the figure covers and what remains for the building, services and applicable approvals.

Q: Should I check the project or my specific wing?

A: Both. The wing containing your flat is essential in a multi-building development.

Q: Is an old MahaRERA update proof of a stalled project?

A: No. It is a reason to request current evidence and an explanation.

Q: Can a sales brochure replace the portal update?

A: No. Compare the brochure’s claims with official disclosures, the agreement and the actual site.

Q: Does a proposed completion date guarantee key handover on that day?

A: No. Read the contract, current official records and the promoter’s documented position.

Sources and Limitations

MahaRERA’s official guidance on quarterly and annual project updates:

https://maharera.maharashtra.gov.in/index.php/guidance-project-update-quarterly-annually

The guidance explains the update fields and promoter obligations. This article does not assess any named project’s compliance or completion date.

Next Steps

Check the registration number and building-wise information before paying the next instalment. Browse homes at https://listifyi.com/properties. Mumbai promoters and agents who present dated, building-specific progress information can explore Listifyi business onboarding at https://listifyi.com/business.

Tags:Mumbai Real EstateMumbai Housingunder-constructionrera-section-11due-diligence

Enjoyed this article?

Share it with your friends and network.

Comments (0)

No comments yet. Be the first to share your thoughts!

Post a Comment

Your email address will not be published. Required fields are marked *

Why Listifyi

About Us

Building video-first property discovery since 2024.

How It Works

Watch, learn, then talk to the seller directly.

Transparency

Listings checked by our team. Buyers connect directly with the seller.

The Listifyi Edge

Knowledge reels from local professionals.

Listifyi

Listifyi

Watch property videos before you visit. We never sell buyer details. Buyers contact the seller directly.

© 2026 Listifyi Innovations Private Limited

CIN U58201KA2024PTC192927 · DPIIT-recognised startup · Bengaluru

LISTIFYI
Mumbai Project Progress: Check The MahaRERA Update Date